[Utility Outage] Completed Control System Outage - 07/21/2014 08:00

Carroll W. Jones jonesc at jlab.org
Fri Jul 25 19:12:59 EDT 2014


The following Control System Outage has been Completed:

Outage:      Swithover to JCI Virtual ADX Server
Proposed By: Carroll W. Jones
Start Time:  07/21/2014 08:00
End Time:    07/23/2014 17:00

Description/Impacts:
Setup a virtual JCI ADXserver (same as current software version) based in the Building 12 Computer Center and transfer all site JCI controllers from the existing physical ADX Server to the virtual ADX Server.

The existing JCI ADX Server will remain operational until the virtual JCI ADX Server is ready to be placed online.  Firmware updates required to enable all existing controllers to communicate with the new JCI ADXserver software will be implemented.   Controller outage periods will vary from a few minutes to about 30-40 minutes depending upon the size and age of the controller.   Efforts will be taken to place critical systems that can not experience the downtime without significant adverse impact to systems supported by equipment controlled by the specific controller being updated.  For example, the Central Chiller System
utilizes multiple controllers and sensors located in various areas across the site to function, system components will be switched to manual operation to not adversely impact site operations such as the F-Wing Data Center, the Accelerator Service Building Chilled Water
Loop, and various site cleanrooms located in the Test Lab and the EEL Building.  Critical Test Lab industrial systems (chemical processing ventilation, Acid Chiller System, and clean room conditioning equipment) have been scheduled to be processed in accordance with SRF Production schedule to minimize possible adverse impacts.

For additional information or clarification, please contact Carroll Jones at 757-876-1778.

Impacted Areas:
	Bldg 01: North LINAC
	Bldg 02: South LINAC
	Bldg 18: Free Electron Laser
	Bldg 21: North Extractor Service
	Bldg 23: Experimental Staging Building
	Bldg 38: South Access
	Bldg 39: East Arc Service
	Bldg 40: West Arc Service
	Bldg 45: West Arc Service
	Bldg 49: East Arc Service
	Bldg 50: East Arc Service
	Bldg 53: Injector Service
	Bldg 56: West Arc Service
	Bldg 63: East Arc Service
	Bldg 67: North Access
	Bldg 68: West Arc Service
	Bldg 72: Physics Storage
	Bldg 82: South Extractor Service
	Bldg 98: Physics Fabrication Building
	Bldg 12: CEBAF Center
	Bldg 55: TED Building
	Bldg 57: Cryogenic Test Facility
	Bldg 58: Test Lab
	Bldg 90: Experimental Equipment Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3



More information about the Fac_outages mailing list