[Utility Outage] Scheduled Power Outage - 06/30/2014 07:00
    Michele Solaroli 
    solaroli at jlab.org
       
    Mon Jul 28 13:12:55 EDT 2014
    
    
  
The following Power Outage has been Confirmed:
Outage:      UIM Electrical Distribution - SOUTH LOOP
Proposed By: Michele Solaroli
Start Time:  06/30/2014 07:00
End Time:    08/02/2014 17:00
Description/Impacts:
South Loop power being fed from LS1, LS2 and LS3 will be shut down from 6/30/14 through 8/02/14.  
For all outage impacts, contact Dianne Owens, Steve Suhring or Walt Akers. Panel board schedules for each building are located in M:\UIM_Interface_Coordination\Electrical Distribution\panel board schedules_2014 as of 12 May 2014
Impacted Areas:
	Bldg 02: South LINAC
	Bldg 56: West Arc Service
	Bldg 68: West Arc Service
	Bldg 82: South Extractor Service
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=11
    
    
More information about the Fac_outages