The following Power Outage has been Proposed:
Outage:      Counting House Emergency Power Outage
Proposed By: Paul Powers
Start Time:  05/08/2014 07:00
End Time:    05/09/2014 15:00
Description/Impacts:
This power outage will be for 8 hours.  The date is preferred for 5/8 or can slip to 5/9.  All power to panels CHEM and CHEMP2 will be secured for 8 hours to finish the construction.  
Impacted Areas:
	Bldg 97: Counting House