[Utility Outage] Scheduled Power Outage - 05/09/2014 07:00
Paul Powers
powersp at jlab.org
Tue May 6 13:30:13 EDT 2014
The following Power Outage has been Confirmed:
Outage: Counting House Emergency Power Outage
Proposed By: Paul Powers
Start Time: 05/09/2014 07:00
End Time: 05/09/2014 17:00
Description/Impacts:
This power outage will be for 8+ hours. All power to panels CHEM and CHEMP2 will be secured for 8 hours to finish the construction.
Impacted Areas:
Bldg 97: Counting House
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=7
More information about the Fac_outages
mailing list