[Utility Outage] Scheduled Power Outage - 05/12/2014 12:00

J. Willoughby jasonw at jlab.org
Mon May 12 11:15:04 EDT 2014


The following Power Outage has been Confirmed:

Outage:      TLA Lighting
Proposed By: J. Willoughby
Start Time:  05/12/2014 12:00
End Time:    05/12/2014 12:10

Description/Impacts:
Remove power from circuit 26 in the TLA.  This will remove just the lights in Room 1012 (CMM), the 2 bathrooms (Rm 1013, 1015), and the 2 gowning rooms (Rm 1054, 1055).  This will only impact normal power lighting.  The emergency lighting should operate as designed (this outage is to verify)

Update:  added room numbers

Impacted Areas:
	Bldg 58: Test Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=9