[Utility Outage] Completed Power Outage - 10/07/2014 06:00
    J.Willoughby 
    jasonw at jlab.org
       
    Wed Oct  8 14:06:14 EDT 2014
    
    
  
The following Power Outage has been Completed:
Outage:      Test Lab Office Area AP-1G-1
Proposed By: J.Willoughby
Start Time:  10/07/2014 06:00
End Time:    10/07/2014 08:00
Description/Impacts:
Remove power from AP-1G-1 to tie in network power.  This impacts all the 208/120 power on the first floor office area of the Test Lab "Area G".
Impacted Areas:
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=8
    
    