[Utility Outage] Scheduled Power Outage - 09/08/2014 12:00

Michele Solaroli solaroli at jlab.org
Thu Sep 4 14:32:02 EDT 2014


The following Power Outage has been Confirmed:

Outage:      UIM Electrical Distribution - End Station Loop
Proposed By: Michele Solaroli
Start Time:  09/08/2014 12:00
End Time:    09/24/2014 17:00

Description/Impacts:
The following Unitsubs will be worked on:  Unitsub T4 - T3 Primary; T4 Secondaries; Unitsub T3 - T2 Primary; T3 and T2 Secondaries; T10 Secondaries; MVSW#4

The following systems will be impacted: 
End Station Refrigeration
Counting House Utility Power; Counting House Computing Power; Elevator
Hall C Utility Power; Hall C Beam Dump; Hall C Clean Power
Hall B Clean Power
Hall A Clean Power

Power to the PSS systems in Hall C and Counting House will be impacted
Counting House Elevator will be offline.  Only those systems on emergency power will not be impacted.

For all outage impacts, contact Dianne Owens, Steve Suhring or Walt Akers. Panel board schedules for each building are located in M:\UIM_Interface_Coordination\Electrical Distribution\panel board schedules 2014 as of 12 May 2014

Impacted Areas:
	Bldg 94: Experimental Hall B
	Bldg 95: Beam Dump Cooling Building C
	Bldg 96: Experimental Hall C
	Bldg 97: Counting House
	Bldg 98: Physics Fabrication Building
	Bldg 101: Experimental Hall A
	Bldg 102: End Station Refrigeration
	Bldg 104: End Station Refrigeration 2

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=12



More information about the Fac_outages mailing list