[Utility Outage] Completed Power Outage - 09/05/2014 08:00
J. Willoughby
jasonw at jlab.org
Fri Sep 5 13:01:03 EDT 2014
The following Power Outage has been Completed:
Outage: North Addition Elevator Repair
Proposed By: J. Willoughby
Start Time: 09/05/2014 08:00
End Time: 09/05/2014 09:00
Description/Impacts:
remove power from P3L5 to repair the elevator feed. This provides power to the cleanroom, DDC, and heaters in the highbay of the North Addition.
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=11