The following Power Outage has been Confirmed:
Outage: Receptacle hook up
Proposed By: Josh Caterbone
Start Time: 08/05/2015 06:00
End Time: 08/05/2015 07:00
Description/Impacts:
Need power outage to hook up circuit for new receptacle Outside wall of 1012 across from 1054 in test lab. Outage will take place from 6am to 7am.
Panel AP-LAB-4 will be affected, and this panel control receptacles on east wall, south wall and room 1012 receptacles on south wall. This also controls the cord reel and VAV.
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=49