The following Road Closure has been Confirmed:

Outage:      Sills at Entrances to Truck Ramps for Hall A & B
Proposed By: Suresh Chandra
Start Time:  08/17/2015 08:00
End Time:    10/01/2015 17:00

Description/Impacts:
Steel Sills are to be installed at Entrances to Truck Ramps for Halls A & B.  During this period vehicular traffic thru the ramps for Hall A & B will be interrupted.  Job will first start at Hall A & then at Hall B.  If you have any questions, please contact me.
Suresh
Tel. 7248


Impacted Areas:
	Bldg 94: Experimental Hall B
	Bldg 101: Experimental Hall A

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=50