The following Power Outage has been Completed:

Outage:      Test Lab Klystron Area
Proposed By: J. Willoughby
Start Time:  08/26/2015 06:00
End Time:    08/26/2015 07:00

Description/Impacts:
Remove power from AP-LAB-18 to tie in power feed for the SSA.  This will remove power from the klystron workstation, CMTF exhaust fan, and the Radcon Monitor for exhaust fan.

Impacted Areas:
	Bldg 58: Test Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=51