[Utility Outage] Scheduled Power Outage - 12/02/2015 06:00
J. Willoughby
jasonw at jlab.org
Tue Dec 1 07:51:55 EST 2015
The following Power Outage has been Confirmed:
Outage: CEBAF F-WING
Proposed By: J. Willoughby
Start Time: 12/02/2015 06:00
End Time: 12/02/2015 08:00
Description/Impacts:
Remove power from the following to tie in additional power for the F-Wing network closets.
*UPDATE*
PANEL RP1A WILL NOT BE INCLUDED IN THIS OUTAGE AT THIS TIME. ALL OTHER PANELS WILL HAVE THEIR POWER REMOVED
Panel RP1A
Remove 120/208 power from the entire first floor, including the kitchen/cafe area
RP2A
Remove 120/208 power from the the entire second floor
RP3A
Remove 120/208 power from the entire third floor
ERPB
Remove emergency 120/208 power from the following
Elevator, F104, F105, Door control, smoke damper, fire shutter, surge suppressor, Fire alarm strobes, F204, F205, F304, F305. This will remove networking capabilities for the entire F-Wing. All emergency power on the second and third floor will be removed
Impacted Areas:
Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=75
More information about the Fac_outages
mailing list