The following Power Outage has been Completed:
Outage:      Power outage for Hall B
Proposed By: Josh Caterbone
Start Time:  01/28/2015 05:00
End Time:    01/28/2015 07:00
Description/Impacts:
Remove Temporary wiring in switchboard ESB.
Impacted Areas:
	Bldg 94: Experimental Hall B
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
    
    