[Utility Outage] Completed Power Outage - 06/27/2015 07:00
Jim Yatzeck
jamesy at jlab.org
Thu Jul 9 17:35:50 EDT 2015
The following Power Outage has been Completed:
Outage: CEBAF F-Wing Outage
Proposed By: Jim Yatzeck
Start Time: 06/27/2015 07:00
End Time: 06/27/2015 15:00
Description/Impacts:
Contractor will be installing new feeders for main electrical switchboard in F-Wing as part of UIM CCCPU project. This will require switchgear to be de-energized. CEBAF F-wing will be without power during this 8-hour outage. Outage meeting scheduled for 6/18 to discuss outage plan in further detail.
Impacted Areas:
Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=28