The following Power Outage has been Completed:
Outage: Bldg 54 and CMSA Power Outage
Proposed By: Paul Powers
Start Time: 07/14/2015 06:00
End Time: 07/14/2015 08:00
Description/Impacts:
Power outage to connect 15 kV power to new transformer. This power outage will be to connect the generator and we expect another power outage for about the same time to disconnect the generator and return to normal power. This date is tentative and a better date will be published as conditions warrant.
Impacted Areas:
Bldg 54: Radcon Calibration
CMSA Parking
CMSA Laydown Area
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=32