[Utility Outage] Scheduled Power Outage - 06/05/2015 07:00
    Josh Caterbone 
    joshuac at jlab.org
       
    Thu Jun  4 08:05:23 EDT 2015
    
    
  
The following Power Outage has been Confirmed:
Outage:      T-Trench area power outage
Proposed By: Josh Caterbone
Start Time:  06/05/2015 07:00
End Time:    06/05/2015 08:00
Description/Impacts:
 I need to de-energize panel DP-LAB-M-4, which is in the T-Trench area.
We need to hook up the circuits we ran in there last week.
This panel controls the following:
Spare in box T-Trench
RO Skid in T-Trench
LEWA Pump in T-Trench
Pressure washer room 1043
Impacted Areas:
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=24
    
    