[Utility Outage] Proposed Power Outage - 06/15/2015 06:00

J. Willoughby jasonw at jlab.org
Mon Jun 8 12:20:12 EDT 2015


The following Power Outage has been Proposed:

Outage:      Test Lab FEL-L1
Proposed By: J. Willoughby
Start Time:  06/15/2015 06:00
End Time:    06/15/2015 15:00

Description/Impacts:
Remove power from FEL-L1 panel.  This will impact the following:

Klystron
All 480 & 120 power on 3rd level with Klystron (DP-LAB-14)
Pair Pump A
CMTF control room power (SNS-P1)
FEL-P1 - (injector ctrl room and cave)
FEL-P2 - (injector ctrl room and cave, CMTF ctrl room)

Impacted Areas:
	Bldg 58: Test Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=18



More information about the Fac_outages mailing list