[Utility Outage] Proposed Power Outage - 06/27/2015 07:00
    Jim Yatzeck 
    jamesy at jlab.org
       
    Fri Jun 12 08:28:41 EDT 2015
    
    
  
The following Power Outage has been Proposed:
Outage:      CEBAF F-Wing Outage
Proposed By: Jim Yatzeck
Start Time:  06/27/2015 07:00
End Time:    06/27/2015 15:00
Description/Impacts:
Contractor will be installing new feeders for main electrical switchboard in F-Wing as part of UIM CCCPU project.  This will require switchgear to be de-energized.  CEBAF F-wing will be without power during this 8-hour outage.  Outage meeting scheduled for 6/18 to discuss outage plan in further detail.
Impacted Areas:
	Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=28
    
    