[Utility Outage] Scheduled Power Outage - 03/11/2015 08:00

MIchele Solaroli solaroli at jlab.org
Fri Mar 6 11:12:31 EST 2015


The following Power Outage has been Confirmed:

Outage:      UIM Electrical Distribution - North Loop
Proposed By: MIchele Solaroli
Start Time:  03/11/2015 08:00
End Time:    03/12/2015 17:00

Description/Impacts:
Contractor will be upgrading cables from Unitsub 5 to MVSW#2 to MH5.  This will impact the test lab chillers and data center redundant feed.  Currently the secondary breaker is off from previous work.  Plan is for a two day outage at Unitsub 5 to remove cables and then re-energize Unitsub 5 for test lab chiller maintenance.  At the end of the maintenance, a 2nd outage (2 days) will occur for contractor to pull cables into Unitsub 5, terminate and test.

Impacted Areas:
	Bldg 58: Test Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2