[Utility Outage] Scheduled Power Outage - 04/01/2015 08:00
    MIchele Solaroli 
    solaroli at jlab.org
       
    Thu Mar 26 14:56:15 EDT 2015
    
    
  
The following Power Outage has been Confirmed:
Outage:      UIM Electrical Distribution - North Loop
Proposed By: MIchele Solaroli
Start Time:  04/01/2015 08:00
End Time:    04/02/2015 17:00
Description/Impacts:
Contractor will be terminating and testing cables from Unitsub 5 to MVSW#2 to MH5.  This will impact the test lab chillers and data center redundant feed.  
Impacted Areas:
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
    
    