[Utility Outage] Scheduled Power Outage - 05/16/2015 07:00
J. Willoughby
jasonw at jlab.org
Tue May 12 09:24:11 EDT 2015
The following Power Outage has been Confirmed:
Outage: Test Lab Outage
Proposed By: J. Willoughby
Start Time: 05/16/2015 07:00
End Time: 05/16/2015 15:00
Description/Impacts:
Replace T-SUB-2 transformer This outage will be conducted on a Saturday and should take ~8 hours. This will remove power from Switchboard 2, which impacts the following:
Highbay 480V and 208V power
The Crane
Both rollup doors
CMTF Doors
Highbay networking
Office area (sec G) power and lighting
Elevator
All of the North Addition (including HDIce, but they have a generator)
I am also installing CTs on both Switchboard 2 and Switchboard 1.Switchboard 1 would impact the following:
Chiller 4
Boilers, hot water pumps
CMTF power/lights
Process Cooling
Acid Chilled Water
LCW pumps
Glycol Pump
Compressed Air
A new breaker will be installed in DP-LAB-4 which will remove power from Rm 1103 and 1109 in the old part of the Test Lab
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=16