[Utility Outage] Scheduled Power Outage - 04/20/2015 07:00

Michele Solaroli solaroli at jlab.org
Thu May 28 14:05:56 EDT 2015


The following Power Outage has been Confirmed:

Outage:      UIM Electrical - CHL Loop Upgrade
Proposed By: Michele Solaroli
Start Time:  04/20/2015 07:00
End Time:    06/02/2015 17:00

Description/Impacts:
UIM Electrical contractor will be upgrading the CHL Loop.  The following unitsubs will be off:  CHL1, CHL2 and CHL AUX.  CHL AUX2 will have an outage in mid-May.  Paul Powers and Jonathan Creel have verified the current CHL settings and confirmed plans for outage.  If you have any questions, please call me at 757-269-7751.

Impacted Areas:
	Bldg 08: Central Helium Liquefier

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=12