[Utility Outage] Completed Power Outage - 05/29/2015 07:30
Michele Solaroli
solaroli at jlab.org
Fri May 29 11:13:25 EDT 2015
The following Power Outage has been Completed:
Outage: UIM Electrical Upgrade - South Loop/FEL
Proposed By: Michele Solaroli
Start Time: 05/29/2015 07:30
End Time: 05/29/2015 10:00
Description/Impacts:
MVSW#3 will be off tomorrow morning for a few hours to allow contractor to demolish cables in preparation for 33MVA to FEL electrical upgrade. This was per Accelerator request to finish South Loop in preparation for helium process the week of 6/15.
There will be a day outage at the FEL to terminate and test cables - anticipated outage date of 6/12. Outage date will be confirmed after progress on installation is evaluated.
Impacted Areas:
Bldg 18: Free Electron Laser
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=22