[Utility Outage] Completed Power Outage - 10/08/2015 09:00
    j. willoughby 
    jasonw at jlab.org
       
    Fri Oct  9 14:41:30 EDT 2015
    
    
  
The following Power Outage has been Completed:
Outage:      test Lab MCC-1B
Proposed By: j. willoughby
Start Time:  10/08/2015 09:00
End Time:    10/08/2015 10:00
Description/Impacts:
Remove power from MCC-1B to install new compressor feed.  This will impact the following
Boilers, hot water pumps
Process Cooling
Acid Chilled Water
LCW pumps
Glycol Pump
Compressed Air
Impacted Areas:
	Bldg 57: Cryogenic Test Facility
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=64
    
    