The following Power Outage has been Proposed:
Outage: Bldg 36 power outages - Panels 36-L1, 36-L4 & 36-L5
Proposed By: Paul Powers
Start Time: 10/23/2015 07:00
End Time: 10/27/2015 08:00
Description/Impacts:
These power outages will be to hookup power for the new lights in the mezzanine and the fans in the High Bay area. The work will start on Friday for about 1 hour (until 8 AM) if the work is not complete, then it will extend to Monday, again from 7 AM to 8 AM. They will start on panels 36-L4 and L5 (Mark Augustine's area and the east end of the building). The other panel, 36-L1, is for the Mag Test Area in the West end (where the crane is, not the adjacent room).
Impacted Areas:
Bldg 36: General Purpose Building
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=66