[Utility Outage] Completed Power Outage - 10/28/2015 08:00
    j. willoughby 
    jasonw at jlab.org
       
    Wed Oct 28 11:50:24 EDT 2015
    
    
  
The following Power Outage has been Completed:
Outage:      Cebaf F-Wing  RP1G & ERPA
Proposed By: j. willoughby
Start Time:  10/28/2015 08:00
End Time:    10/28/2015 10:00
Description/Impacts:
Remove power from RP1G and ERPA to tie in new circuits
RP1G will impact all 120/208 power in rooms F109, F110, F111, F111B, F111A
ERPA will impact the fire alarm system and fire alarm compressed air suppression systems.
Impacted Areas:
	Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=67
    
    