The following Power Outage has been Confirmed:

Outage:      CTF Power Outage - Cryo Systems
Proposed By: Andrew Crumbly
Start Time:  10/08/2015 09:00
End Time:    10/08/2015 13:00

Description/Impacts:
Main electric power for the CTF building and associated cryogenic equipment will be turned off for 4 hours on October 8th to allow for connection of temporary power wires to the systems and equipment in support of CTF building construction activities. Additional activities in this outage include new air compressors tie-ins in the basement of the test lab. Significant construction activity will continue in the CTF area at this time and affected personnel are advised to remain out of the area on east side of building 57.

Impacted Areas:
	Bldg 57: Cryogenic Test Facility
	Bldg 58: Test Lab