[Utility Outage] Completed HVAC Outage - 04/17/2016 07:00

Mike Sprouse msprouse at jlab.org
Mon Apr 18 09:38:53 EDT 2016


The following HVAC Outage has been Completed:

Outage:      Bldg. 12 B-Wing Heating Piping Leak Repair
Proposed By: Mike Sprouse
Start Time:  04/17/2016 07:00
End Time:    04/17/2016 17:00

Description/Impacts:
Must repair a water leak on the hot water heating system in B-Wing. Affects heat for Wings A,B & C. Must isolate and drain a portion of the heating system to make repair. Work area Rm B204.
*Heat is normally scheduled OFF during weekend = no change in building temperature during repair.

Impacted Areas:
	Bldg 12: CEBAF Center

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=106