The following Power Outage has been Confirmed:

Outage:      Test Lab MMC-1B
Proposed By: j. willoughby
Start Time:  08/10/2016 07:00
End Time:    08/10/2016 09:00

Description/Impacts:
Remove power from MCC-1B to tie in new circuits into bucket 5/1 and 5/2.  This will remove power from the following:


CMTF Test Cave 120/208 Power
LCW Pump
58-PCP-a
58-PCP-2
58-ACP-1
58-ACP-2
58-CWP-1
PCH-1
GSP-1
Air Compressor 2

Impacted Areas:
	Bldg 58: Test Lab