[Utility Outage] Completed Power Outage - 08/11/2016 05:00

Josh Caterbone joshuac at jlab.org
Tue Aug 16 09:07:29 EDT 2016


The following Power Outage has been Completed:

Outage:      Breaker replacement at FEL (18)
Proposed By: Josh Caterbone
Start Time:  08/11/2016 05:00
End Time:    08/11/2016 06:00

Description/Impacts:
see below for what will be affected:

U-400 VIA T-11			
U300 VIA T10			
480V REC. RM 205			
480V REC. RM 210			
CHILLER DOWNSTAIRS			
LIGHTING 209-210			
LIGHTING 206-208			
LIGHTING 200-204			
LIGHTING 205			
CLEAN ROOM 			
CLEAN ROOM 
CLEAN ROOM VIA T-212			
WATER HEATER				
AHU-11				
AHU-10				
AHU-9A			
LIGHTING 211-23			
LIGHTING 215-216			
LIGHTING OUTDOOR			
LIGHTING 205				
REC. 205 CORD REEL			
REC. RM 205			
REC. RM 205			
DISPLAY SIGN			
AHU-3B			
3P REC. 205			
3P REC. 205				
AHU-2B	
REC. 205 CORD REEL			
EF-6			
TVSS				
AHU-3A				
3P REC. 204	
EXTENSION CORD CABINET			
REC. 107			
REC. 107			
REC. 201			
REC. 201			
REC. 201			
WATER COOLER			
AC-1 INDOOR			
HEAT TAPE			
WATER HEATER & REC.			
ACCENT LTS LOBBY			
VIDEO MONITOR LOBBY					
AC-1 OUTDOOR					
REC. 107			
REC. 107			
REC. 105 106 HEAT TAPE LOADING DOCK			
REC. 104, 105 PIT			
REC. 100, 101, 102			
REC. 201, 202, 203			
REC. 201			
REC. 201			
ELEVATOR 120V			
EF-2			
CONF. RM FLR REC.		
AHU-12				
AHU-2A			
			

Impacted Areas:
	Bldg 18: Free Electron Laser

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3