[Utility Outage] Proposed Power Outage - 12/06/2016 09:00
    J. Willoughby 
    jasonw at jlab.org
       
    Mon Dec  5 10:25:46 EST 2016
    
    
  
The following Power Outage has been Proposed:
Outage:      Data Center Wall Outlets
Proposed By: J. Willoughby
Start Time:  12/06/2016 09:00
End Time:    12/06/2016 10:00
Description/Impacts:
Remove power from panel RP1F. This will remove power from all the wall outlets in F112.
Impacted Areas:
	Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
    
    