The following General Outage has been Confirmed:
Outage: Installation of Generator Pad/Generator for DATA Center
Proposed By: Russell Mattox
Start Time: 12/13/2016 08:00
End Time: 02/10/2017 08:00
Description/Impacts:
Close off parking spaces from 90A to Hadron Drive (19 SPACES) - relocate parking space for government vehicle
Reason: installation of generator pad / generator for the DATA Center
Impacted Areas:
Bldg 90: Experimental Equipment Lab