[Utility Outage] Completed Power Outage - 01/08/2016 12:00
J. Willoughby
jasonw at jlab.org
Tue Jan 12 12:25:20 EST 2016
The following Power Outage has been Completed:
Outage: Test Lab DP-LAB-8
Proposed By: J. Willoughby
Start Time: 01/08/2016 12:00
End Time: 01/08/2016 13:00
Description/Impacts:
Remove power from DP-LAB-8 to tie in new cave door operator. Impacts are as follows
AHU-10 (CMTF)
AHU-9 (CMTF Control Room)
Cave Door 2
Welding Receptacles in Staging Area outside CMTF
All 120/208 receptacles in Staging Area outside CMTF
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=81
More information about the Fac_outages
mailing list