[Utility Outage] Scheduled Road Closure - 01/25/2016 08:00
Suresh Chandra
chandra at jlab.org
Wed Jan 13 15:02:17 EST 2016
The following Road Closure has been Confirmed:
Outage: Installation of Concrete Shielding Blocks for Cryo Module Test Cave
Proposed By: Suresh Chandra
Start Time: 01/25/2016 08:00
End Time: 01/29/2016 05:00
Description/Impacts:
Up date: The installation is now planned to be done in the week of Jan 25, 2016 & will take two days. Exact date will be notified later.
Concrete Shielding Blocks for Cryo Module Test Cave will be installed on Jan. 19 & 20, 2016. The overhead door on the west wall of Test Lab High Bay will remain blocks for quite some time. Also High Bay floor area in front of Cryo Module Test Cave and up to the overhead door will remain blocked for the installation. For any questions, please call Suresh Chandra at 269-7248.
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=83