[Utility Outage] Completed HVAC Outage - 01/07/2016 08:30

Carroll W. Jones jonesc at jlab.org
Tue Jan 19 11:28:40 EST 2016


The following HVAC Outage has been Completed:

Outage:      CEBAF Center F-Wing Data Center Cooling Unit 12-CRAC-7 Outage
Proposed By: Carroll W. Jones
Start Time:  01/07/2016 08:30
End Time:    01/07/2016 13:00

Description/Impacts:
Shutdown F-Wing Data Center Cooling Unit 12-CRAC-7 to modify electrical power conduit in new F-Wing Pump Room (former UPS Battery Room).  The unit will be off for approximately 4 hours beginning at 8:30 AM.  Portable circulation fans will be used to blow cool air towards electronic server rack  by 12-CRAC-7 and pull hot air away from the electronic rack.  Computer Center personnel will monitor server performance and additional fans will be setup if required.

For additional information or clarification, please contact Carroll W. Jones at 757-876-1778.

Impacted Areas:
	Bldg 12: CEBAF Center