[Utility Outage] Completed Power Outage - 01/28/2016 08:00
    j. willoughby 
    jasonw at jlab.org
       
    Tue Jan 26 11:17:25 EST 2016
    
    
  
The following Power Outage has been Completed:
Outage:      Test Lab - North Addition
Proposed By: j. willoughby
Start Time:  01/28/2016 08:00
End Time:    01/28/2016 09:00
Description/Impacts:
Remove power from P3H4 in the Test Lab North Addition.  This will impact all the 480/277 power on the second floor of the north annex. This will impact a few Air Handlers in the North Addition as well
Impacted Areas:
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=82
    
    