The following Power Outage has been Proposed:
Outage:      Data Center Partial Outage - 250 kVA UPS and PDU-8
Proposed By: Paul Powers
Start Time:  06/30/2016 08:00
End Time:    06/30/2016 12:00
Description/Impacts:
Power outage to install two breakers in Maintenance Bypass Panel.  Will secure UPS and PDU.  Per Chip Watson, equipment affected is backed up by PDU-6.  Outage is expected to take 4 hours.
Impacted Areas:
	Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=122
    
    
More information about the Fac_outages