The following Power Outage has been Completed:
Outage: Tie in circuits for golf/gem cart chargers.
Proposed By: Josh Caterbone
Start Time: 06/30/2016 06:00
End Time: 06/30/2016 06:30
Description/Impacts:
Panels AP-1-1 sections 1 and 2 will lose power. They feed the following:
Receptacles in the corridor, exterior, rooms 1501, 1503, 1504, 1505,1511, 1513, 1515, 1554, 1556, kitchen area, plasma TV, watt stopper repeater, automatic door, general receptacle under D.
This outage will take approx. 30 minutes.
Impacted Areas:
Bldg 55: TED Building