[Utility Outage] Scheduled Power Outage - 03/31/2016 07:00
    J. Willoughby 
    jasonw at jlab.org
       
    Tue Mar 29 10:56:15 EDT 2016
    
    
  
The following Power Outage has been Confirmed:
Outage:      Test Lab EAP-1200
Proposed By: J. Willoughby
Start Time:  03/31/2016 07:00
End Time:    03/31/2016 08:30
Description/Impacts:
Remove power from EAP-1200.  This will remove 120 emergency power from emergency receptacles in the CMTF Control room. This includes the PSS rack. This will also remove power from the East network racks which will interrupt networking in the ITF and CMTF control rooms.
Impacted Areas:
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=102
    
    
More information about the Fac_outages
mailing list