The following Power Outage has been Completed:
Outage: Arc Power Outage to replace breaker
Proposed By: Josh Caterbone
Start Time: 05/10/2016 06:00
End Time: 05/10/2016 06:30
Description/Impacts:
Brief power outage to replace a 100 amp breaker.
Impacts are: Receptacles in rooms 100,103A,124,128,129,130,132,153--Lights in rooms 125,126,127. Bandsaw in room 103, Remote Chiller #1, Chiller, Recirculating pumps 1 and 2, Fan EF-9, Vacuum pump, Unit Heater, Air compressor #2 and #3, Domestic Water Pump
Impacted Areas:
ARC: Advanced Research Center