The following HVAC Outage has been Completed:
Outage: Repair Leak in ARC Lab AHU-1 Heat Recovery Piping
Proposed By: Carroll W. Jones
Start Time: 10/05/2016 05:00
End Time: 10/05/2016 08:00
Description/Impacts:
The ARC laboratory air handler AHU-1 must be secured to locate and repair a leak in its heat recovery coil piping. The minimize formation of condensation in the lab area hallways and labs, the laboratory exhaust system will be turned off while the AHU-1 is off. Please secure all open chemicals while the laboratory ventilation system is off.
For additional information or clarification, please contact Carroll Jones at 757-876-1778.
Impacted Areas:
ARC: Advanced Research Center