The following Power Outage has been Proposed:

Outage:      CEBAF Center Panel RP1G & RP1H
Proposed By: Paul Powers
Start Time:  07/10/2017 07:00
End Time:    07/10/2017 07:30

Description/Impacts:
Power Outage to remove Temporary feed to the Warwick Construction Trailer.  The actual outage should take less than 15 minutes.  It will not affect the Cafeteria.  It will affect Dave Abbott's Lab and the other rooms along the corridor from the elevator to the mechanical room.  It will also affect the JCI panel in Rm 142.

Impacted Areas:
	Bldg 12: CEBAF Center

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=4