[Utility Outage] Scheduled Power Outage - 07/20/2017 05:00
Paul Powers
powersp at jlab.org
Wed Jul 19 14:14:35 EDT 2017
The following Power Outage has been Confirmed:
Outage: CEBAF Center F-Wing Emergency Electrical Systems
Proposed By: Paul Powers
Start Time: 07/20/2017 05:00
End Time: 07/20/2017 05:30
Description/Impacts:
Power outage to Emergency Panels at the F-Wing electrical Room. Affect panels EPP, ERPA and ERPB. This will NOT affect the Cafeteria. It will affect the Data Center Chilled Water. Those VFDs will be put in "Hand" before the outage and put in "Auto" after the outage. Outage is being done to correct overheating condition in the Automatic Transfer Switch serving the Emergency Panels.
Impacted Areas:
Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=9
More information about the Fac_outages
mailing list