[Utility Outage] Scheduled HVAC Outage - 07/26/2017 10:30
Mike Sprouse
msprouse at jlab.org
Tue Jul 25 16:36:02 EDT 2017
The following HVAC Outage has been Confirmed:
Outage: ARC Process Chiller Maintenance (Edwards Chiller)
Proposed By: Mike Sprouse
Start Time: 07/26/2017 10:30
End Time: 07/24/2017 10:45
Description/Impacts:
Performing general preventative maintenance on the Edwards process chiller : chilled water flow will STOP for ~ 30 min during task. Items in the Lab(s) Wing, 1st-3rd floors, cooled by this system should be secured (off / powered down) during the outage as there will be NO flow or cooling available from the process chilled water system.
Comfort cooling will remain ON and fully operational.
Impacted Areas:
ARC: Advanced Research Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3
More information about the Fac_outages
mailing list