[Utility Outage] Completed HVAC Outage - 03/07/2017 08:30

Mike Sprouse msprouse at jlab.org
Tue Mar 7 11:15:30 EST 2017


The following HVAC Outage has been Completed:

Outage:      Annual Testing of Smoke Detectors in AHUs - EEL
Proposed By: Mike Sprouse
Start Time:  03/07/2017 08:30
End Time:    03/07/2017 09:30

Description/Impacts:
Testing duct smoke detectors in building air handlers : each AHU will shut down for ~ 2 minutes when "action" is tested on the fire system (trip the detectors)

Impacted Areas:
	Bldg 90: Experimental Equipment Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1



More information about the Fac_outages mailing list