The following Power Outage has been Completed:
Outage:      Test Lab EAP-1200
Proposed By: j. willoughby
Start Time:  11/08/2017 07:00
End Time:    11/08/2017 08:00
Description/Impacts:
Remove power from EAP-1200 to tie in emergency receptacles for LCLS2 staging area.  This will remove all 120 emergency power from the following
Network cabinets NW1 & NW2
CMTF COntrol Room (Includes PSS rack)
Assembly Area
Emergency Panel EAP-LAB-1 which includes the emergency receptacles above the injector test cave
Impacted Areas:
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1
    
    