[Utility Outage] Completed Power Outage - 11/13/2017 07:00
j. willoughby
jasonw at jlab.org
Wed Nov 15 07:16:28 EST 2017
The following Power Outage has been Completed:
Outage: ESHQ B52 - UPS Power
Proposed By: j. willoughby
Start Time: 11/13/2017 07:00
End Time: 11/13/2017 08:00
Description/Impacts:
BUILDING 52
Remove power from UPS-P1. This will remove 208/120 power from the following
Pyrolyser
Red receptacles in Rm 31, 20, and 22
Impacted Areas:
Bldg 52: EHS&Q Building
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2