The following Power Outage has been Confirmed:
Outage:      Test Lab High Bay AP-LAB-14
Proposed By: J. Willoughby
Start Time:  10/25/2017 07:00
End Time:    10/25/2017 08:00
Description/Impacts:
Remove power from AP-LAB-14 to tie in receptacles for LCLS2 area.  This will remove all 208/120 power from the following:
CM Test Cave Staging
Shipping/Receiving & CM Staging
Impacted Areas:
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
    
    
More information about the Fac_outages
mailing list