[Utility Outage] Scheduled Road Closure - 10/31/2017 07:00

winslow winslow at jlab.org
Mon Oct 30 15:57:29 EDT 2017


The following Road Closure has been Confirmed:

Outage:      Sanitary Sewer Repairs at West ARC
Proposed By: winslow
Start Time:  10/31/2017 07:00
End Time:    11/10/2017 17:00

Description/Impacts:
Excavate and repair leaking sanitary sewer at West ARC. Portions of parking near the Injector Building will be closed to allow subcontractor access to work site, equipment storage, etc. 

Impacted Areas:
	Bldg 45: West Arc Service
	Bldg 53: Injector Service

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3



More information about the Fac_outages mailing list