The following Gas Outage has been Proposed:

Outage:      Test Lab/TED/HD ICE - Nitrogen gas system outage to add backup port to gas line 
Proposed By: Ronald Bartek
Start Time:  02/17/2018 08:00
End Time:    02/17/2018 13:00

Description/Impacts:
Main gas line providing nitrogen gas to the Test Lab, TED Bldg., HD Ice will be turned off to allow a contractor to install a shop fabricated spool piece that incorporates a port for future rental LN2 tank/vaporizer that will be installed in the near future while the existing leaking LN2 tank is replaced with a new tank.

Impacted Areas:
	Bldg 55: TED Building
	Bldg 58: Test Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1